Party Wall Award – If there is a dispute (the Adjoining Owner does not consent) then a Party Wall Award is require to outline the requirements of the works to be carried out.
- Building Owners Surveyor (excluding underpinning & basements) – The Building Owner is the one carrying out the works and will pay for all/majority of the costs towards the Award. This includes:-
- Land Registry Search Fees to verify Adjoining Owner(s) identity & address;
- Providing explanatory notes;
- Form of Consent;
- Serving the notice (by recorded delivery and by person if local);
- Providing follow up ‘Ten Day Notices’ if the neighbour fails to respond within 14 days;
- The drafting, negotiating and agreeing the Award with the Adjoining Owners Surveyor (if not Agreed Surveyor);
- Serving of the Party Wall Award;
- Including a schedule of Condition survey in the Adjoining Owners Property.
The price for a Party Wall Award under Section 1 or 3 is a Fixed Fee of £550.
The price for a Party Wall Award under Section 6 for excavations (basements or underpinning) is a Fixed Fee of £1250.
- Adjoining Owners Surveyor – The Adjoining Owner is the neighbour to the Building Owner carrying out the works. The Adjoining Owner is able to consent, dissent or provide a counter notice for the works carried out. This includes;
- A description of the works being undertaken
- The agreed protection measures to the adjoining owner’s property
- Method statements for the contractor to adhere to
- Access statements for the contractor to adhere to
- Clarification of the formal procedures in the event of damage or issue
- A timescale for the duration of the works
- The Schedule of Condition Report
We charge an hourly rate of £175 but can at the request of the Building Owner agree a FIXED FEE in advance.
- Agreed/Joint Surveyor – An Agreed Surveyor acts for both the Building Owner(s) and Adjoining Owner(s).
This includes;
- Act for both Building Owner and Adjoining Owner
- Land Registry Search Fees to verify Adjoining Owner(s) identity & address – if different to agreed owners;
- Providing explanatory notes;
- Form of Consent;
- Serving the notice (by recorded delivery and by person if local);
- Providing follow up ‘Ten Day Notices’ if the neighbour fails to respond within 14 days;
- The drafting, negotiating and agreeing the Award ;
- Serving of the Party Wall Award;
- Including a schedule of Condition survey in the Adjoining Owners Property.
The price for a Party Wall Award under Section 1 or 3 is a Fixed Fee of £750.
The price for a Party Wall Award under Section 6 for excavations (basements or underpinning) is a Fixed Fee of £1500.